Punta Gorda Waste Water Treatment Plant

Supply and erect 2-buildings for the City of Punta Gorda at the Punta Gorda Waste Water Treatment Plant facility on Bermont Road. The project consisted of one 40’-0” x 100’-0” Inland Buildings Pre-engineered Metal Building and the other was a 80’-0” x 100’-0” Pre-engineered Metal Building supplied by Inland Buildings. Additional work included cutting and placing new Pier Pad Columns, forming and pouring a Perimeter Concrete Foundation, Overhead Doors, Service Doors, Mechanical Wall Vents, Operable Ridge Vents, and Sky-lite Panels in the FR 26-Ga. Inland Roof System. This project was completed in 8-weeks which also included the demolition of the wind damaged 80’-0” x 100’-0” Metal Building.